Status
Under construction

Length
240 km

Voltage
230 kV

Capacity
900 MVA

COD (estimado)
2022

This project consists of a 230-kV transmission line connecting the Oriximiná substation (Pará) with the Jurupari substation (Pará) and ultimately the Parintins substation (Amazonas). The concession includes the constructive challenge of crossing the Amazon River where it flows through the Óbidos district, with a span of 2.3 km at a height of 254 m.

This infrastructure will meet electricity demand in the districts located on both sides of the Amazon River, especially in the cities of Oriximiná, Óbidos and Juruti (Pará), and the city of Parintins (Amazonas state).